Multivariate model optimisation during the implementation of flexible interconnection projects for MV distribution networks
, , , , et
17 mars 2025
À propos de cet article
Publié en ligne: 17 mars 2025
Reçu: 05 nov. 2024
Accepté: 17 févr. 2025
DOI: https://doi.org/10.2478/amns-2025-0186
Mots clés
© 2025 Xing Su et al., published by Sciendo
This work is licensed under the Creative Commons Attribution 4.0 International License.
Figure 1.

Figure 2.

Figure 3.

Figure 4.

Figure 5.

Figure 6.

Figure 7.

Figure 8.

Figure 9.

Figure 10.

Figure 11.

The performance of different policies is the result of the comparison
Scheme | Operating cost/CNY | Voltage deviation/p.u. | Total work loss/kWh |
Initial system | — | 0.0870 | 4865.45 |
Scheme 1 | 1559.5 | 0.081 | 3332.0 |
Scheme 2 | 5543.8 | 0.0746 | 2897.3 |
Scheme 3 | 3696.1 | 0.0685 | 2655.2 |