Optimization of Cultural and Creative Product Development Process Based on Digital Intelligent Manufacturing Technology
, e
29 set 2025
INFORMAZIONI SU QUESTO ARTICOLO
Pubblicato online: 29 set 2025
Ricevuto: 31 dic 2024
Accettato: 30 apr 2025
DOI: https://doi.org/10.2478/amns-2025-1117
Parole chiave
© 2025 Li He et al., published by Sciendo
This work is licensed under the Creative Commons Attribution 4.0 International License.
Figure 1.

Figure 2.

Figure 3.

The process optimization is compared to the period
| Activity | Optimized acquired number | Optimized the day before | Save days |
|---|---|---|---|
| Scheme design | 11 | 13 | 2 |
| Evaluation design feasibility | 3 | 5 | 2 |
| Apply for raw materials | 7 | 13 | 6 |
| Competition analysis | 2 | 6 | 4 |
| Product development design | 12 | 15 | 3 |
| Mould design/test module | 29 | 35 | 6 |
| Design validation | 2 | 4 | 2 |
| Testing | 6 | 11 | 4 |
| Replacement sample | 10 | 13 | 3 |
| Trial quantity | 14 | 17 | 3 |
| Intermediate sample production | 1 | 1 | 0 |
| Tot | 97 | 133 | 36 |
The development cost savings after process optimization
| R&d cost | Unit (yuan per day) | Save days after optimization | Savings cost (yuan) |
|---|---|---|---|
| Employee salary | 500 | 36 | 18000 |
| Other expenses | 200 | 36 | 7200 |
| Total cost | 700 | 25200 |
The process optimization is compared to the target
| Evaluation project | Optimized target | Process optimization | Process optimization | Reach a ratio |
|---|---|---|---|---|
| Product development cycle | 13 weeks | 19 weeks | 13.86 weeks | 93.8% |
| Quantity of new product development process documents | 85 | 140 | 90 | 94.4% |
| Product verification pass rate | 96% | 92% | 96% | 100% |
| Profit and tax profit | >85% | 80% | 92% | 100% |