Optimization of Cultural and Creative Product Development Process Based on Digital Intelligent Manufacturing Technology

,  and   
Sep 29, 2025

Cite
Download Cover

Figure 1.

Process reconstruction 7 step model
Process reconstruction 7 step model

Figure 2.

Venter product development plan
Venter product development plan

Figure 3.

Venter product development plan and actual comparison
Venter product development plan and actual comparison

The process optimization is compared to the period

Activity Optimized acquired number Optimized the day before Save days
Scheme design 11 13 2
Evaluation design feasibility 3 5 2
Apply for raw materials 7 13 6
Competition analysis 2 6 4
Product development design 12 15 3
Mould design/test module 29 35 6
Design validation 2 4 2
Testing 6 11 4
Replacement sample 10 13 3
Trial quantity 14 17 3
Intermediate sample production 1 1 0
Tot 97 133 36

The development cost savings after process optimization

R&d cost Unit (yuan per day) Save days after optimization Savings cost (yuan)
Employee salary 500 36 18000
Other expenses 200 36 7200
Total cost 700 25200

The process optimization is compared to the target

Evaluation project Optimized target Process optimization Process optimization Reach a ratio
Product development cycle 13 weeks 19 weeks 13.86 weeks 93.8%
Quantity of new product development process documents 85 140 90 94.4%
Product verification pass rate 96% 92% 96% 100%
Profit and tax profit >85% 80% 92% 100%