Dynamic Management Operations Scheduling Strategy for Hybrid Manufacturing Production Line Based on Data Twin and Robotics Technology
17 mar 2025
O artykule
Data publikacji: 17 mar 2025
Otrzymano: 29 wrz 2024
Przyjęty: 26 sty 2025
DOI: https://doi.org/10.2478/amns-2025-0313
Słowa kluczowe
© 2025 Jianjia Qi, published by Sciendo
This work is licensed under the Creative Commons Attribution 4.0 International License.
Figure 1.

Figure 2.

Figure 3.

Figure 4.

The production of artifacts is time-consuming and time-consuming (s)
| Link classification | Time consuming before optimization | Optimized after time |
|---|---|---|
| Workpiece | 26.32 | 11.14 |
| Workpiece handling and marking | 12.47 | 6.34 |
| Workpiece to specify position (position) | 38.73 | 18.67 |
| Placement of workpiece | 5.37 | 2.24 |
| Workpiece to specify position (position) | 55.42 | 24.36 |
| Grab the workpiece to the processing center | 28.75 | 13.28 |