Research on the application of optimization algorithms in engineering management and its practice in project scheduling

 y   
21 mar 2025

Cite
Descargar portada

Figure 1.

Method of earning value method
Method of earning value method

Figure 2.

Application Flow Chart of Earned Value Method
Application Flow Chart of Earned Value Method

Figure 3.

Bridge project network plan
Bridge project network plan

BCWP in September

Project Labor cost Mechanical charge Materials cost Subcontract charge Total
A 383520 0 452337 653114 1488971
B 0 189925 0 125262 315187

January earnings report (yuan)

Project Earning indicator Labor cost Mechanical charge Materials cost Subcontract charge Total
C BCWS 0 282205 0 183649 465854
BCWP 0 292270 0 119431 411701
ACWP 0 173462 0 148991 322453
SV 0 10065 0 -64218 -54153
CV 0 118808 0 -29560 89248
F BCWS 5197 337946 6352 383687 733182
BCWP 5370 313978 6563 333477 659388
ACWP 6348 391597 7757 393491 799193
SV 173 -23968 211 -50210 -73794
CV -978 -77619 -1194 -60014 -139805

March earnings report (yuan)

Project Earning indicator Labor cost Mechanical charge Materials cost Subcontract charge Total
F BCWS 0 337945 0 383687 721633
BCWP 0 344447 0 376788 721235
ACWP 0 340815 0 374564 715379
SV 0 6502 0 -6899 -397
CV 0 -3632 0 2224 -1408

Activity time calculation results

Activity name Node number Earliest starting time Earliest end Late start time The end of the day Total jet lag Free time Critical path
i j ES EF LS LF TF FF
A 2 4 0 39 0 41 0 0 Yes
B 2 3 0 40 43 81 41 2
C 5 8 40 213 40 213 0 0 Yes
D 3 6 40 172 83 214 41 42
E 4 4 40 171 83 216 41 41
F 7 7 215 226 212 226 0 0 Yes
G 9 8 222 252 223 253 0 0 Yes
H 8 10 254 266 252 266 0 0 Yes
I 11 11 267 296 268 296 0 0 Yes
J 11 14 297 304 299 311 4 5
K 10 10 267 287 278 295 10 10
L 12 13 297 309 297 311 0 1 Yes
M 14 15 309 314 311 316 0 0 Yes
N 15 18 315 345 314 344 0 1 Yes

Overall budget cost of the bridge (yuan)

Job code Labor cost Materials cost Mechanical charge Subcontract charge Total
A 605473 520304 767861 1467259 3389434
B 257294 308712 180754 377083 1119964
C 961406 2607521 672386 0 4255290
D 409299 402371 128379 1372563 2276823
E 302136 3207985 197519 2587247 6339379
F 66159 111796 17829 0 137554
G 446764 1700776 843782 0 2967724
H 156520 51294 111419 0 322795
I 208400 809385 77505 0 1076794
J 101399 181768 85429 0 324085
K 300746 308623 140331 528012 1260523
L 82781 36100 56878 0 225736
M 167781 395465 184476 0 711779
N 98412 -11208 125391 0 216151

BCWS in September

Project Labor cost Mechanical charge Materials cost Subcontract charge Total
A 332580 399100 0 597651 1331500
B 0 0 167993 16700 267400

ACWP in September

Project Labor cost Mechanical charge Materials cost Subcontract charge Total
A 387965 0 463537 659742 1511245
B 195003 130002 325005

December earnings report (yuan)

Project Earning indicator Labor cost Mechanical charge Materials cost Subcontract charge Total
C BCWS 0 729029 0 1261547 1990576
BCWP 0 771914 0 1234122 2006036
ACWP 0 599040 0 1305983 1905023
SV 0 42884 0 -27424 15460
CV 0 172874 0 -71861 101013
F BCWS 5197 337946 6352 383687 733182
BCWP 5023 293721 6140 333477 638361
ACWP 5937 366332 7258 393831 773358
SV -174 -44225 -212 -50210 -94821
CV -914 -72611 -1118 -60353 -134996

April earnings report (yuan)

Project Earning indicator Labor cost Mechanical charge Materials cost Subcontract charge Total
F BCWS 0 327044 0 371310 698354
BCWP 0 344476 0 375446 719922
ACWP 0 326078 0 370279 696357
SV 0 17431 0 4136 21567
CV 0 18397 0 5167 23564
G BCWS 0 149604 0 6029 155633
BCWP 0 160309 0 6448 166757
ACWP 0 139447 0 5871 145318
SV 0 10705 0 419 11124
CV 0 20861 0 577 21438
H BCWS 246592 369889 287691 0 904172
BCWP 247690 369984 291723 0 909397
ACWP 246370 369680 286582 0 902632
SV 1098 95 4032 0 5225
CV 1320 305 5141 0 6766

The project is expected to be in the construction period

Specific project (working package) Planned period
Bridge September 10, 2022, October 20, 2022
Precast beam field September 10, 2022, October 20, 2022
Bridge foundation (punch pile, column, beam) October 20, 2022 ~ April 11, 2023
Hollow plate prefabrication October 24, 2022 ~ March 4, 2023
Box girder prefabrication October 24, 2022 ~ March 4, 2023
Support stone April 11, 2023 ~ April 21
Beam mounting April 22, 2023 ~ May 20
Reaming May 21, 2023 ~ June 5
Bridge dress June 6, 2023 ~ July 5
Expansion joint installation July 6, 2023 ~ July 15
Fence construction June 6, 2023 ~ June 25
Sideway board installation July 6, 2023 ~ July 20
Marking line July 20, 2023 ~ July 25
The bridge is demolished by the way July 26, 2023 ~ August 20

October earnings report (yuan)

Project Earning indicator Labor cost Mechanical charge Materials cost Subcontract charge Total
A BCWS 265534 0 318652 477978 1062164
BCWP 272265 0 302342 574132 1148739
ACWP 259999 0 328249 589875 1178123
SV 6731 0 -16310 96154 86575
CV 12266 0 -25907 -15742 -29383
B BCWS 0 134064 0 89376 223440
BCWP 0 101564 0 67710 169274
ACWP 0 97501 0 65001 162502
SV 0 -32500 0 -21667 -54167
CV 0 4063 0 2709 6772
C BCWS 0 399790 0 691816 1091606
BCWP 0 421356 0 703985 1125341
ACWP 0 405801 0 662896 1068697
SV 0 21565 0 12168 33733
CV 0 15555 0 41089 56644
D BCWS 0 0 0 377977 377977
BCWP 0 0 0 311473 311473
ACWP 0 0 0 291616 291616
SV 0 0 0 -66503 -66503
CV 0 0 0 19858 19858
E BCWS 0 0 0 521209 521209
BCWP 0 0 0 536471 536471
ACWP 0 0 0 556466 556466
SV 0 0 0 76200 76200
CV 0 0 0 -19995 -19995

November earnings report (yuan)

Project Earning indicator Labor cost Mechanical charge Materials cost Subcontract charge Total
C BCWS 0 705512 0 1220852 1926364
BCWP 0 747013 0 1194311 1941324
ACWP 0 681280 0 1185224 1866504
SV 0 41501 0 -26541 14960
CV 0 65733 0 9087 74820
D BCWS 0 0 0 667016 667016
BCWP 0 0 0 681461 681461
ACWP 0 0 0 669281 669281
SV 0 0 0 14444 14444
CV 0 0 0 12180 12180
E BCWS 0 0 0 822962 822962
BCWP 0 0 0 767074 767074
ACWP 0 0 0 835649 835649
SV 0 0 0 -55888 -55888
CV 0 0 0 -68575 -68575

September earnings report (yuan)

Project Earning indicator Labor cost Mechanical charge Materials cost Subcontract charge Total
A BCWS 337964 0 405557 608336 1351857
BCWP 383520 0 452337 653114 1488971
ACWP 387965 0 463537 659742 1511244
SV 45556 0 46779 44779 137114
CV -4445 0 -11200 -6628 -22273
B BCWS 0 170628 0 113752 284380
BCWP 0 189925 0 125262 315187
ACWP 0 195003 0 130002 325005
SV 0 19297 0 11510 30807
CV 0 -5078 0 -4740 -9818

Bridge project work relationship

Job code Job name Preorder Duration/d
A Bridge 42
B Precast beam field 43
C Bridge foundation (punch pile, column, beam) A 175
D Hollow plate prefabrication B 131
E Box girder prefabrication B 135
F Support stone C 12
G Beam mounting D, E, F 26
H Reaming G 18
I Bridge dress H 25
J Expansion joint installation I, K 10
K Fence construction H 23
L Sideway board installation I, K 26
M Marking line J, L 6
N The bridge is demolished by the way M 35

Total cost deviation (yuan)

Month May June July
Total cost deviation 19091 23846 48569

The earning method is compared to the traditional cost control method

Earning parameter Critical path earning method Traditional cost control method
Completed budget cost (BCWP) 3291297
Actual costs (ACWP) 3257403 3257403
Budget costs (BCWS) 3276398 3276398
Cost deviation 33894 18994
Progress deviation 14899

February earnings report (yuan)

Project Earning indicator Labor cost Mechanical charge Materials cost Subcontract charge Total
F BCWS 0 305241 0 346556 651797
BCWP 0 344531 0 352467 696998
ACWP 0 363857 0 364420 728277
SV 0 39290 0 5911 45201
CV 0 -19326 0 -11953 -31279